Curing is a critical step of the installation process because the solvent cement must dry completely before you fill the pipes with water and test for leaks. If you were to pressurize and test the system before allowing the solvent cement to fully evaporate, you increase the chance of inadvertently damaging joints.
To help avoid this issue, this resource explains what’s happening as a joint cures, how long you should wait to pressure test a system, and some variables that can affect cure times.
Solvent cement is the substance used to join chlorinated polyvinyl chloride (CPVC) pipe and fittings. When solvent cement is applied to the surface of a pipe and fitting, it softens the material surfaces of each piece. As the pipe and fitting are pressed together, the softened surfaces of the pieces intertwine and fuse together.
As the solvent cement evaporates, the material surface hardens, locking the two pieces together. This process is called “curing.”
When all the solvent cement has evaporated, the joint is considered fully cured, and can safely be pressure tested.
You should consult with the solvent cement manufacturer to identify the recommended cure times. That said, the table below provides general solvent cement curing recommendations.
Different variables can affect how quickly the solvent cement can evaporate out of a joint. Each of the following should be considered:
We want to make sure you get the support and information you need for your project. If you have any questions about FlowGuard® CPVC pipe and the appropriate cure times specific to your solvent cement, our team of piping system consultants is ready to talk.